CASE STUDY
EAST MIDLANDS
PSP RENEWALS
DELIVERING RESILIENT POWER INFRASTRUCTURE THROUGH FULLY INTEGRATED TURNKEY DELIVERY
CLIENT
Network Rail
LOCATION
East Midlands Route
DURATION
2 Years
SERVICES
Design | Engineering | Civil | Manufacturing | Electrical | Test & Commissioning
OVERVIEW
Kent Group successfully delivered the East Midlands PSP Renewalsproject in collaboration with the Network Rail East Midlands E&P Route Engineering team.
Delivered over a two-year period from contract award through to final entry into service, the programme involved the turnkey renewal of three critical Principal Supply Point (PSP) sites across the East Midlands route:
Uttoxeter–30kVA UPS / 88kVA Generator
Market Harborough–40kVA UPS / 88kVA Generator
Syston–80kVA UPS / 145kVA Generator
The project formed part of Network Rail’s CP6 renewals work bank, with the objective of improving the long-term reliability, resilience and maintainability of critical signalling power infrastructure.

PROJECT BY NUMBERS
2
Years
3
PSP Buildings
0
Accidents
30-80kVA
UPS Systems
3
DNO Supplies
0
Lost Time Injuries
THE CHALLENGE
Multi-site Programme
Managing three complex renewals across multiple operational locations.
Live Railway
Maintaining operational signalling power throughout delivery.
Complete Integration
Coordinating civil, electrical, mechanical and DNO interfaces.
Programme Certainty
Delivering every stage through one integrated team.
THE SOLUTION
Kent Group delivered a complete turnkey solution encompassing civil, electrical and signalling design, procurement, in-house manufacture of Principal Supply Points, site clearance, foundations, compound construction, DNO coordination, installation, testing and final commissioning. By integrating every discipline within one delivery team, the programme achieved safe, efficient delivery while maintaining operational railway performance.
SCOPE OF WORKS
-
Civil Engineering Design
-
Electrical Design
-
Signalling Design Coordination
-
Principal Supply Point Manufacture
-
Site Clearance
-
Foundations
-
Roads & Compounds
-
DNO Connections
-
Building Installation
-
Electrical Installation
-
Testing
-
Commissioning
CLIENT BENEFITS
Improved Operational Resilience
Multi-disciplinary delivery
Reduced Maintainance Risk
Increased Future Capacity
Future-proof power infrastructure
Single Point of Accountability
"The East Midlands PSP Renewals programme perfectly demonstrates what Kent Group is capable of delivering. Successfully completing a multi-site programme of this scale required exceptional collaboration, engineering expertise and careful coordination across every discipline.
From initial design through to in-house manufacture, civil construction, electrical integration and final commissioning, every team played a vital role in the successful delivery of these critical infrastructure upgrades.
I’m incredibly proud of the professionalism and commitment shown throughout the programme and would like to thank Network Rail for their collaborative approach and the trust they placed in Kent Group. Together, we've delivered infrastructure that will improve the resilience and reliability of the railway for many years to come."
​
Tom Kent
Commercial and Planning Director
DIRECTORS STATEMENT
PROJECT GALLERY