CASE STUDY
VICTORIA RE-SIGNALLING
PHASE 3
PROVIDING SPECIALIST SIGNALLING POWER EXPERTISE IN SUPPORT OF ONE OF THE UK's LARGEST RAILWAY MODERNISATION PROGRAMMES
CLIENT
Siemens Mobility
LOCATION
London, UK
DURATION
2.5 Years
SERVICES
Design | Engineering | Manufacturing | Electrical | Test & Commissioning
OVERVIEW
As part of the Victoria Area Re-signalling Programme, Kent Group was appointed by Siemens Mobility to deliver specialist signalling power infrastructure works in support of one of the UK's largest railway modernisation programmes.
Delivered over a 2.5-year period, our scope focused on the design integration, manufacture, installation and commissioning of critical signalling power assets across multiple operational locations within the Victoria route.
​
Working collaboratively as part of Siemens Mobility's wider delivery team, Kent Group provided the specialist electrical engineering expertise required to successfully integrate new Principal Supply Points (PSPs), Functional Supply Points (FSPs), DNO supplies and associated signalling power infrastructure into a live operational railway. Through careful planning, close collaboration and disciplined delivery, the project enhanced network resilience while supporting the successful delivery of the wider Victoria Re-signalling Programme.

PROJECT BY NUMBERS
2.5
Years
4
PSP Buildings
0
Accidents
24
Functional Supply Points
6
DNO Supplies
7km
Cable Installed
THE CHALLENGE
Live Railway
Maintaining operational signalling power throughout delivery.
Future Network Capacity
Designing infrastructure capable of supporting future phases of the Victoria Re-signalling Programme through spare feeder capacity and auto reconfiguration systems.
Stakeholder Collaboration
Working closely with Siemens Mobility and Network Rail to coordinate engineering, commissioning and staged delivery.
THE SOLUTION
Kent Group delivered a comprehensive signalling power solution comprising four new Principal Supply Points, six new DNO supplies, twenty-four Functional Supply Points, new 650V feeder arrangements and approximately seven kilometres of signalling power cabling. The programme also incorporated Auto Reconfiguration equipment and Power Management Systems (PMS/SCADA), providing enhanced monitoring, operational flexibility and resilience while creating capacity for future expansion.
SCOPE OF WORKS
-
Electrical Design
-
Principal Supply Point Manufacture
-
Functional Supply Points
-
DNO Connections
-
650V Feeders
-
Power Management Systems
-
Auto Reconfiguration Equipment
-
Cable Infrastructure
-
Testing
-
Commissioning
CLIENT BENEFITS
Improved Operational Resilience
Improved power management
Reduced Maintainance Risk
Increased Future Capacity
Future-proof power infrastructure
Safe delivery within a live railway
"Successful rail infrastructure programmes are built on strong partnerships.
Victoria Re-signalling Phase 3 is a great example of how specialist expertise, close collaboration and a shared commitment to delivery can achieve outstanding results. Working alongside Siemens Mobility, we were able to provide the signalling power expertise needed to support this important programme, helping to deliver infrastructure that will improve the resilience and performance of the railway for years to come.
I'd like to thank Siemens Mobility and Network Rail for the collaborative approach taken throughout the project, which was fundamental to its success."
​
Tom Kent
Commercial and Planning Director