CASE STUDY
LNE SIGNALLING POWER DISTRIBUTION RENEWALS
DELIVERING ONE OF OUR LARGEST RAIL INFRASTRUCTURE PROGRAMMES THROUGH ENGINEERING EXCELLENCE, COLLABORATIVE DELIVERY & CONSISTENT EXECUTIONS
CLIENT
Network Rail
LOCATION
LNE Route
DURATION
4 Years
SERVICES
Design | Engineering | Civil | Manufacturing | Electrical | Test & Commissioning
OVERVIEW
Awarded as part of Network Rail's CP6 Electrification & Plant programme, the LNE Signalling Power Distribution Renewals represented the largest contract in Kent Group's history. Approximately 44 kilometres of the LNE Route between Doncaster and Scunthorpe, the programme involved the renewal and enhancement of critical signalling power infrastructure through a fully integrated, multi-disciplinary delivery model.
Kent Group successfully delivered the complete programme, encompassing engineering, civil infrastructure, electrical installation, in-house switchgear manufacture and final testing and commissioning. Working safely within a live operational railway, the project introduced new Principal Supply Points, Auxiliary Supply Points, Functional Supply Points, upgraded 650V distribution feeders and extensive new cable infrastructure, all delivered through a carefully phased implementation strategy.
The completed programme has significantly improved the resilience, reliability and maintainability of the route's signalling power network, providing modern infrastructure that will support safe and reliable railway operations for many years to come.

PROJECT BY NUMBERS
180
FSPs
92
Ground Bases
32
Equipment
Platforms
2
Under Track Crossings
>44km
Route Renewed
57km
Cable
4
DNO Supplies
33
Stagings
11
650v Feeders
11
REBs
4
PSPs
4
ASPs
THE CHALLENGE
Managing Programme Scale
Coordinating engineering, manufacturing and delivery across multiple sites while maintaining programme consistency.
Live Railway Integration
Renewing critical signalling power infrastructure while maintaining operational railway services.
Stakeholder Coordination
Working collaboratively with Network Rail, designers, manufacturers and delivery partners across numerous work locations.
Resource Management
Maintaining programme momentum through effective planning, logistics and deployment of specialist engineering teams.
CLIENT BENEFITS
Improved Operational Resilience
Multi-disciplinary delivery
Reduced Maintainance Risk
Increased Future Capacity
Future-proof power infrastructure
Improved Asset Reliability
THE SOLUTION
Kent Group developed a phased delivery strategy, beginning with extensive civil infrastructure works including GRP trough routes, foundations, retained bases and screw pile installations. This was followed by the installation of signalling power cabling, Functional Supply Points, Principal Supply Points, Auxiliary Supply Points and a new 6+2 track Under Track Crossing. Through carefully planned staged commissioning, signalling power was successfully transferred onto the new resilient 650V distribution network while maintaining operational continuity throughout the programme.
"The LNE Signalling Power Distribution Renewals programme represents a significant milestone in Kent Group's growth and demonstrates our ability to successfully deliver large-scale infrastructure programmes.
Coordinating multiple workstreams, engineering disciplines and operational interfaces over several years required exceptional teamwork, careful planning and a shared commitment to safety and quality.
I'm incredibly proud of everyone involved in the programme and grateful to Network Rail for their collaborative approach throughout.
Together, we've delivered infrastructure that will provide lasting benefits for the railway and reinforce the value of strong, long-term partnerships."
Robert Kent
Operations Director
DIRECTORS STATEMENT
SCOPE OF WORKS
Civil Engineering Design
Electrical Design
Signalling Design Coordination
In House Switchgear Manufacture
Site Clearance
Foundations
Roads & Compounds
DNO Connections
Building Installation
Electrical Installation
Testing
Commissioning